“Replacement mesh for the screen” is not yet a usable spare-parts request. The supplier needs to know which machine, which deck and which installed media arrangement the buyer means. For a plant planning maintenance, replacement screen media should be treated as an identifiable assembly item rather than a piece of material ordered by approximate length and width.
The immediate goal is an accurate replacement enquiry. A separate process review may be appropriate if the plant wants a different cut or operating result. Mixing those two tasks can lead to an order that neither reproduces the existing arrangement nor has enough information for a deliberate change.
Record the machine model, serial or project reference where available, and the relevant drawing revision. For a YK vibrating screen, identify the exact installed configuration rather than relying on a general catalogue image. Keep site photographs linked to the machine reference.
Name the deck and position using a shared convention. A description such as “the middle panel” can mean different things when viewed from opposite ends of the machine. Use the supplier's drawing references or an agreed marked arrangement so both parties identify the same location.
If the machine has more than one media size or configuration, list them separately. Do not assume a spare from one vibrating screen deck will fit another because the overall screen width is the same. Retain the exact position of every item in the enquiry.
Ask what screen aperture specification controls the installed media. Record the opening shape and dimensions, material and other details specified by the equipment supplier. A broad word such as mesh does not always identify the construction clearly enough for procurement.
If a mesh-count term is used, ask the supplier to define it and state the associated opening information. Do not translate an opening requirement into a count based on an assumption about wire thickness or construction. Use a controlled specification that both parties understand.
Distinguish replacement from process modification. An exact replacement enquiry should describe the approved installed item. If a different aperture or media type is proposed, share the intended process objective and ask the responsible equipment team to assess the change. A catalogue resemblance is not evidence of equivalent screening behaviour.
The outside dimensions do not describe the whole fit. Photograph and document the edges, hooks, fixing points or modular interfaces used by the actual arrangement. Ask which drawing controls those features and whether associated clamps or fastening parts belong in the order.
Record the orientation of the item in the deck. A sketch with clear direction references is more useful than a loose sample photographed without identifying which edge faces the feed end. Keep any manufacturer's assembly marks with the supporting record.
| Part of the specification | Information to record | Common ambiguity to remove |
|---|---|---|
| Machine and deck | Model, project reference and deck position | Which installed location is involved? |
| Opening | Shape, dimensions and defined terminology | What separation opening is requested? |
| Media construction | Approved material and construction details | What item is actually being supplied? |
| Outer geometry | Dimensions and drawing references | Which overall shape must fit? |
| Edge and attachment | Hooks, fixings or interface features | How is it secured in this deck? |
| Associated parts | Approved clamps and fastening requirements | What else is needed for the change? |
Ask the supplier to review the complete specification before confirming supply. If a field is unknown, mark it as unresolved rather than silently copying it from a different spare.
A removed item can help identify construction and attachment features, but its condition may no longer represent the original geometry. Record wear, distortion or damaged areas when sending measurements or photographs. Do not assume an approximate dimension from a damaged panel is the nominal manufacturing dimension.
Where possible, compare the item with the equipment records and a known approved spare. Ask the supplier which features can be used for identification and which need the original drawing. This is particularly useful when the machine has received past modifications that are not reflected in an old parts list.
Keep the original item or an agreed reference until the enquiry is resolved, if site procedures permit. Photographs should include identification and views of the relevant details. A distant image of the assembled screen rarely shows enough information for an unambiguous attachment specification.
Ask for the manufacturer's replacement procedure and any required associated parts. Plan the work through competent maintenance personnel following the site's isolation and equipment procedures. Procurement should not invent a fitting sequence or tightening requirement to fill a missing instruction.
Consider access and handling before the planned shutdown. Check the actual replacement item's dimensions against the intended removal route and maintenance arrangement. A spare can be correctly manufactured while the site still needs a practical plan for reaching and handling it.
If a different media construction is proposed, ask which parts of the existing support or attachment arrangement require review. Do not accept an apparently convenient substitute on the assumption that every deck can accommodate it without other changes.
After receiving inspection, update the site's parts record with the actual approved configuration. The next buyer should not have to reconstruct the same information from an unlabelled worn panel.
A good replacement screen media request tells the supplier exactly what must fit and tells the maintenance team exactly where it belongs. Keep the machine identity, aperture specification and attachment details together, and separate a routine replacement from a proposed process change before placing the order.
Machinery Weight 53-62t
Max Feeding size(mm) ≤600mm
Hopper Volume(m³) 80-360t/h
Machinery Weight 55-57t
Max Feeding size(mm) ≤215mm
Hopper Volume(m³) /
Machinery Weight 33-35t
Max Feeding size(mm) 150-400t/h
Hopper Volume(m³) 2.5
Machinery Weight 33t
Max Feeding size(mm) 150-400t/h
Hopper Volume(m³) 7m³
Machinery Weight 54-63t
Max Feeding size(mm) ≤600mm
Hopper Volume(m³) /
Machinery Weight 9.5-75t
Max Feeding size(mm) ≤1000mm
Hopper Volume(m³) 61-1204t/h
Just let we know what you want, and we will get in touch with you as soon as possible!